After three acquisitions, a company runs four ERPs and three CRMs. How do you rationalize the portfolio?

Short answer

Build an inventory linked to capabilities and costs, assess each system with business and technical fitness (TIME), define the target per capability considering processes, data migration and contracts, then sequence consolidation by value and risk, starting with low-risk wins, and track savings and decommissioning.

Detailed answer

  1. Inventory and map: systems → capabilities → users, data, integrations, costs, contracts (renewal dates matter).
  2. Assess: business fit, technical fitness, compliance, vendor viability; TIME classification.
  3. Target state per capability: usually one CRM and one ERP (or ERP + specialized systems), chosen by fit, scale and strategic direction (e.g. cloud ERP).
  4. Process harmonization: the hard part; agree on standard processes with business owners before migrating.
  5. Data strategy: master data consolidation, migration rules, historical data archiving.
  6. Sequencing: quick wins (CRM consolidation often simpler), contract renewal windows, business calendar (avoid year-end for finance).
  7. Governance: benefits tracking, decommission milestones, executive sponsorship.

Architecture diagram

flowchart LR
  A1[ERP A] --> MIG[Data migration & MDM]
  A2[ERP B] --> MIG
  A3[ERP C] --> MIG
  MIG --> T[Target cloud ERP]
  C1[CRM 1] --> CT[Target CRM]
  C2[CRM 2] --> CT
  T <--> INT[Integration platform] <--> CT

Follow-up questions

  • How do you keep the business running during consolidation? (Integration layer for coexistence; phased cutover by entity or region.)

What the interviewer expects

Linking systems to capabilities and money, emphasis on process and data, realistic sequencing.

Common mistakes to avoid

Treating it as a pure technology migration; ignoring contract dates and change management.